Entelliteq SeaPort-e Quality Assurance
At Entelliteq, Quality Assurance (QA) is built into our company-wide Process Improvement work. An independent Engineering Process Group (EPG) performs and oversees these activities, reporting directly to Entelliteq’s COO.
Each Project Plan is where our QA process starts, so the Project Manager (PM) builds quality in from day one. Across the project lifecycle, the PM uses Entelliteq’s document and reporting templates to keep work complete, consistent, and continuous from one project to the next. Entelliteq’s Project Management processes are defined in an integrated set of Handbooks that adopt the industry-recognized de facto software development standard as both the guide for process improvement and the benchmark to meet. Using this standard also lets us gauge how far improvements have advanced.
At project start, the PM sends a draft Project Management Plan (PMP) to the EPG for review and feedback. The EPG evaluates the PMP against all applicable policies, procedures, and regulations. When every known requirement is met, the EPG signs off to confirm the plan has passed a quality assurance review, then assigns an EPG representative to the project.
Process Reviews are scheduled ahead of time at Senior Management’s discretion throughout the project lifecycle. Their frequency depends on the project’s size and duration, and the first review is held within one month of project start.
During a Project QA Review, the EPG representative—independent of the project and team—evaluates project activities and work products by checking artifacts against the PMP and the designated standards and procedures to confirm compliance. The representative first compares the PMP and other artifacts to the checklist, forming a preliminary view of how closely activities and work products follow Entelliteq’s standard processes. The representative then sets up interviews with the PM and other staff as needed to complete the evaluation using our standard Process Review Checklist.
The EPG representative then analyzes the information gathered and drafts a QA Review Report, which may include Opportunities To Improve (OTIs) and/or Corrective Action Requests (CARs). The report uses these notations:
– Investigate Further (IF) = Action Item for EPG
– Follow-up Required (FOR) = Action Item for EPG
– Opportunity to Improve (OTI) = Suggestion to Project Manager/Team
– Corrective Action Request (CAR) = Request for Corrective Action to the Project Manager/Team
The EPG representative then meets with the PM to review the Draft Project Review Report together.
Working together, the EPG representative and PM build a shared understanding of the QA Review Report and its Action Items, OTIs, and CARs. Action Items are the points the EPG representative must follow up on between Project Process Reviews, and they fall into two categories: Investigate Further (IF) or Follow-Up Required (FOR). OTIs are improvement suggestions the EPG representative offers the project team. CARs are corrective actions the project team must take to comply with CESA processes or another regulation or standard.
Based on that meeting, the EPG representative prepares a final process Review Report, attaching any OTIs and/or CARs in an Excel spreadsheet. The final report and its attachments go to the PM and COO, and the PM is expected to review the findings with the team. At least once every three months, the overall EPG gives the COO a quarterly review summarizing all process reviews and follow-up activities.
Within one week of the Project Process Review Report being distributed, the PM assigns each CAR to the appropriate team member with a due date and tells the EPG representative that date. The EPG representative monitors CAR progress and tracks each one to closure. If a CAR cannot be resolved at the project level, the EPG representative escalates it to the COO. The EPG representative also maintains a list of action items found during the QA review for follow-up, categorized as “Investigate Further” or “Follow up Required.”
Entelliteq’s QA policies give management clear visibility into the processes a project uses. QA means reviewing process activities and work products to confirm they follow the applicable standards, regulations, policies, and procedures, and the review results are shared with the project manager and Senior Management. Senior Management decides how much of Entelliteq’s QA resources go to which projects. Through this QA process and its reviews, we ensure every deliverable is clear, compliant, well-presented, and complete. After a review, the EPG representative confirms all defects are resolved and certifies the deliverable before it goes to the client.
Monitoring and Controlling Costs
A central element of the Project Management Plan is the Project Monitoring and Control (PMC) Plan, which always treats cost as a core metric. Entelliteq treats Monitoring and Controlling Costs as an integral part of overall Project Monitoring and Control. The PM builds a project PMC Plan using the Entelliteq PMC Plan template. The specific measures gathered may vary by project type and size, but cost is always included. The project’s set of metrics is confirmed with EPG and COO approval. At minimum, monitoring and control cover size, effort, cost/budget, schedule, and the status of high-level risks, and other measurements may be added when the project calls for them.
Once a Task is awarded, the PM meets with the project team—or folds this into the Project Kickoff—to plan how cost and performance metrics will be collected and reported. That planning covers how often data is collected, analyzed, reported, and reviewed in meetings. Team members are then assigned specific duties for gathering and reporting measurements.
We track measurements of cost status, project commitments, risks, and stakeholder involvement. Team members regularly report estimated and actual effort spent on tasks, and they periodically report task attributes such as size and complexity. The PM tracks progress against the schedule timeline, recording actual completion of activities and milestones, and also compares project costs against the budget.
Any significant deviation from planned parameters is flagged. Measurements are stored in a repository so the current project can reference them and future projects can benefit from them as well.
The PM prepares and submits a Project Status Report to the EPG, the COO, and—as appropriate—other stakeholders named in the PMP, with reporting frequency also documented in the PMP. Each report includes regular status against the project planning and risk parameters along with any issues identified. Any measurement that has crossed management thresholds or could keep the project from meeting its objectives must be raised with the EPG and COO. The actions to take are:
– If the project is “on track,” simply keep collecting and analyzing project measures.
– If the project is not “on track” but the issues fall within the PMP’s scope, plan appropriate corrective action and manage it to closure while continuing to collect and record project measurements.
– If the project is not “on track” and one or more issues fall outside the PMP’s scope, decide whether to a) revise the PMP to address the issues, or b) request a Change Order to resolve them and then revise the PMP accordingly.